Retrofit Project Diary: Warnham Road - Blog 4 - ECD Architects Retrofit Project Diary: Warnham Road - Blog 4

Posted by at 4:29PM on 17 January 2011

Timber frame, 22/12/10 By Ruairi Kay

The front and rear infill panels have been removed and most of the new timber frame has been installed. The build up for the frame is: plasterboard and skim finish, Intello plus vapour and air barrier, 125mm deep timber frame with Celotex PIR insulation tightly fitted between. This is then finished with ply. In the new year Walltec, (the external wall insulation sub contractor), will then fix 60mm Phenolic insulation over this, finished in a silicon render. Overall u-value is 0.13 W/m2K. The concrete panel elements will be clad in vacuum insulated panels, more about this in the new year.

I MG 9540

The rear elevation with new timber frame and most of the windows fitted

We have had some problems with the window and doors fitting the openings on site on this project as well. It appears that the timber frame installation differs from what was originally designed, resulting in a smaller opening in two incidents. We have however been able to switch the windows around, meaning we only need to re order one of the windows.

I MG 9536

The front elevation